挑战
The client needed to upgrade an existing production area to ISO 7 while minimizing downtime and keeping material flow efficient. Traditional multi-vendor coordination was causing schedule risk.
方案
We supplied a coordinated package: modular wall/ceiling system, personnel air showers with interlock, material pass-through with conveyor interface, and FFU layout. Design was matched to the existing building constraints.
成果
•Cleanliness target achieved and verified
•Installation completed within planned window
•Reduced personnel traffic into the clean zone
•Single documentation package simplified customer internal audit